|
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
New Underground Facility The Project TransGas Energy Systems LLC (TGE) is proposing to construct and operate the TransGas Energy Facility (the Project or Facility), a 1,100-megawatt (MW) cogeneration facility on the East River between the Greenpoint and Williamsburg's North Side sections of Brooklyn. The proposed Facility will also be capable of producing up to 2 million pounds per hour (mmlbs/hr) of steam for export to Con Edison's steam distribution system in Manhattan . Prior to construction and operation of the Project, TGE must, pursuant to Article X of the Public Service Law, obtain a Certificate of Environmental Compatibility and Public Need (Certificate) from the New York State Board on Electric Generation Siting and the Environment (Siting Board). An Article X Application for the Project was filed in December 2002, and following the submittal of additional information, the Application was determined to be in compliance with New York Public Service Law § 164 in June 2003. The hearing process commenced in July 2003 and concluded with a recommended decision in April 2004. This document constitutes an Amendment of the Article X Application, as provided for in the Siting Board Order issued on September 15, 2004. Review of the Project is proceeding under Siting Board Case No. 01-F-1276. This Amendment
to the Article X Application presents an underground design for the
proposed Project. This underground design was developed to mitigate
the perceived land use and visual impacts from the original aboveground
design for the Project. Except for the replacement of the air-cooled
condenser with a once-through cooling water system, nearly all of the
plant components and operating characteristics remain unchanged from
the original aboveground design.
To address this requirement of the Order, TGE requests the following authorizations: First, TGE requests that the certificate authorize a six-month period for TGE to negotiate with New York City for the use of Newtown Creek WPCP effluent. If New York City continues to refuse to provide the effluent, then TGE would be authorized in the certificate to substitute noncondensing “topping” turbines for the steam turbine generators, which would eliminate the need for condenser cooling and once-through cooling water. The Facility would operate solely in the cogeneration mode, producing electricity and steam, as would the East River Repowering Project being built by Con Edison. Newtown Creek WPCP effluent, however, would no longer be needed. With this modified configuration, steam output is maintained with only a minimal reduction in electricity generation, and the balance of the plant equipment remains unchanged.
As described
in the Article X Application the Facility will be fueled primarily by
natural gas with very low-sulfur distillate as a backup fuel. Natural
gas will be delivered by pipeline operated by KeySpan Energy Delivery
(KeySpan), operator of the local natural gas system. Backup fuel oil
will be delivered to the Project site via an existing on-site petroleum
pipeline operated by the Buckeye Pipeline Company and barge deliveries.
The Facility will provide electric power to the New York City transmission
cable system operated by the New York Independent System Operator (NYISO).
Power will be delivered at the highest system voltage, 345 kilovolts
(kV), connecting to nearby existing underground cables. The
Siting Board Order of September 15, 2004 The
Board also stated that TGE must file an amendment in accordance with
the Board's regulations, and also addressing various issues identified
by the Board. This Amendment explains the underground design. Pursuant
to guidance provided by New York Department of Public Service (DPS)
Staff, the Amendment does not repeat unnecessarily what is currently
in the Article X Application, and which is not proposed to be amended.
Rather, the Amendment states where the original proposal as described
in the Article X Application would change based upon building most of
the Facility underground The Siting Board Order issued on September
15, 2004 did not request TGE to propose new certificate conditions.
Based upon the compiled record and briefs that have been filed in the
proceeding, TGE is prepared, upon the request of the Examiners, to update
the proposed certificate conditions for the Project, asamended.
View the Engineering Feasibility Report TEXT in.pdf (June 30, 2004) |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||